NEPRA granted generation license to 50MW Cacho Wind power project in 2017. The project is indevelopment stage and has been added in the list of ‘actively promoted energy projects’ of CPEC. Sourcehttp://cpec.gov.pk/project-details/79https://gwadarpro.pk/2450/renewable-energy-like-wind-and-solar-power-emphasized-in-cpec

1320 MW Thar Mine Mouth coal-fired power plant by Oracle was listed as ‘actively promoted project ofCPEC’ on November 8, 2014. Oracle’s Block VI Thar coal project elevated to the priority list in during the6 th JCC of CPEC held in December 2016. However, the project faced issues like determination of coaltariffs, risk coverage guarantees […]

The PPIB issued LOS with the authority to develop Azad Pattan Hydropower project in June 2016. It waslisted as ‘energy actively promoted project’ of CPEC in the 9th JCC held in 2019. The project, at anestimated cost of $ 1,600 million, is being developed by China Gezhouba Group Company (CGGC). Thedevelopment process is at an […]

In August 2014, the Kohala Hydropower project was listed as ‘actively promoted’ project of CPEC. Theproject, being built on the Jhelum River in AJK, is estimated to cost $ 2,400 million. The project has beenawarded to Kohala Hydropower Company Ltd as Pakistan signed tripartite agreement with China in 2020 Funded by China, this is the […]

The China Communications Construction Company (CCCC) was nominated in 6 th JCC, held in December2016, to undertake the development of 300MW coal-fired power project at Gwadar. PPIB issued theletter of interest on May 26, 2017 while LOS was issued in August 2019. The groundbreaking of projectheld in November 2019. Source http://cpec.gov.pk/project-details/5https://www.ppib.gov.pk/gawadar300mw_4nov19.htmhttps://nepra.org.pk/tariff/Tariff/Petitions/2018/Revised%20Tariff%20Petition%20CIHC.pdf

The groundbreaking of the Karot Hydropower Project held during the visit of Chinese President XiJinping in April 2015. The construction work began in December 2016. Over 4000 jobs have beencreated during the construction phase. Project achieved the critical milestone of River Closure inSeptember 2018. With 90% work done, the project is expected to be completed […]

PPIB signed Implementation Agreement with S.K Hydro (Pvt) Limited for development of 870 MW SukiKinari Hydropower project at an estimated cost of $ 1.8 billion to be established in Mansehra, KhyberPakhtunkhwa (KP). The land acquisition and financial close and of project were achieved in 2016-17respectively. 70% work on project is completed whereas it created over […]

Hub Power Company Limited is setting up 330 MW Thar coal based power project at Thar Block-II, Sindh. Private Power and Infrastructure Board (PPIB) issued LOS in December 2016. Over 70% work on project is completed, creating 805 jobs during the construction phase. Sourcehttp://cpec.gov.pk/project-details/73https://www.ppib.gov.pk/publications/PPIB%20Annual%20Report%202016-17.pdfhttps://www.hubpower.com/growth-aspirations/

The Economic Coordination Committee (ECC) on July 25, 2017 approved transmission line project Implementation Agreement (IA) and Transmission Services Agreement which were subsequently executed on May 14, 2018. The construction work started in 2018. With an estimated cost of $ 1658.3 million, project completed on September 1, 2021. Total 2212 jobs were created during the […]